Haripriya Sai v. State of Odisha
Case brief
What is this about?
Orissa High Court writ petition disposed of on ground of available statutory alternative remedy; Lower Suktel Irrigation Project Bolangir; land acquisition compensation paid but rehabilitation and resettlement benefit denied; Section 64 Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013; petitioner directed to pursue remedy under Section 64 of the Act; no adjudication on merits of R&R entitlement.
What did the court decide?
Observation that the Petitioner, if so advised, may avail the remedy under Section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in accordance with law. ¶19