M/S D.D Builders Limited, Kalahandi v. State of Odisha
Case brief
What is this about?
Petitioner sought escalation of price in a construction contract. Court observed Superintending Engineer's recommendation was pending approval. Directed Chief Construction Engineer to consider recommendation within four weeks.
What did the court decide?
Directed Chief Construction Engineer to consider Superintending Engineer's recommendation within four weeks.