Nishikanta Mahapatra v. State Project Director,Opepa
Service law – Disengagement notice dated 02.05.2016 (Annexure-8)
Case brief
What is this about?
WP(C) No. 2884 of 2018, Nishikanta Mahapatra v. State Project Director, OPEPA & Ors., High Court of Orissa at Cuttack, Justice Biraja Prasanna Satapathy, order dated 05.11.2024 - disengagement notice dated 02.05.2016 (Annexure-8), natural justice, appealable order, alternative remedy, liberty to file appeal, delay condonation, writ petition disposed of.
What did the court decide?
Writ petition disposed of with liberty to file an appeal before the appellate authority within two weeks; the appellate authority to decide the appeal on merit without insisting on delay. ¶19