Gopinath Das v. State of Orissa
Case brief
What is this about?
Gopinath Das and others v. State of Odisha and others; OPTCL; High Tension conductor/line drawn over petitioner's private land; Khata No.13, mouza Shyamraipur, Balasore Tahasil; HT line from Balasore Grid Supply station to Somanathpur; remedy routed to Collector, Balasore via grievance petition; ratio of Executive Engineer (Electrical), TPCODL v. Soubhangini Patra (AIR 2023 Ori 86) applied/followed; four-week filing window; six-month decision window with hearing; writ petition disposed 04.10.2024; single-judge bench (K.R. Mohapatra).
What did the court decide?
Petitioner directed, if so advised, to approach the Collector, Balasore within four weeks with a comprehensive grievance petition and relevant documents, in terms of the ratio in Executive Engineer (Electrical), TPCODL and another v. Soubhangini Patra and another (AIR 2023 Ori 86); Collector, Balasore to decide within six months thereafter after hearing the parties and communicate the result to the petitioner.