and price escalation for the extended period in terms of provisions of the Agreement under clause-31(e) of the conditions of the contract under Annexure-1. Payment of such amount has been recommended by opposite party no.4 to the Financial Advisor-cum-Joint Secretary to the Govt. But the same has not been adhered to till date. But fact remains, on the basis of document under Annexure-6 series dated 07.05.2012, wherein the petitioner has already contended that opposite party no.5 has already recovered huge amount from his bill and requested to close his contract with immediate effect and pay his legitimate dues without further delay. On the request made vide Annexure-6, the Chief Engineer & Basin Manager, Subarnarekha & Budhabalanga Basin, Laxmiposi issued letter dated 05.01.2017 under Annexure-9 series to the Financial Adviser-cum-Joint Secretary to the Government of Odisha, Department of Water Resources, Bhubaneswar indicating as follows: