M/S C.P.Mohanty v. State of Odisha
Case brief
What is this about?
The High Court quashed an order imposing a penalty on a contractor for delayed work completion. The court held that applying a code provision regarding termination penalties was unjustified since the contract was extended rather than terminated.
What did the court decide?
Annexure-23 is quashed to the extent of levy of penalty @ 0.25%; Opposite Parties directed to release withheld bill value within two months.