Maithili Dehury v. State of Odisha
Case brief
What is this about?
The Court directed the Zone Officer, Land Acquisition, Rengali Dam Project to dispose of an application filed by the petitioner under Section 28-A of the Land Acquisition Act, 1894, for determining compensation amount within two months.
What did the court decide?
Direction to the Zone Officer to decide the application under Section 28-A of the Land Acquisition Act, 1894 within two months.