Suresh Ch.Panda and an v. State and Ors.
Case brief
What is this about?
This PIL directs the opposite parties to complete the construction of Drain No. 7 in Bhubaneswar by the onset of the next monsoon of 2020, subject to land acquisition and fund allocation, granting liberty to revive the petition if necessary.
What did the court decide?
Direction for completion of construction of Drain No. 7 by the onset of the next monsoon of 2020, subject to land acquisition and fund allocation, with liberty to revive the petition if needed.