Minati Mallick v. State of Odisha
Case brief
What is this about?
In a writ petition, the petitioner sought a transfer application form for a plot in the Bidanasi Project Area. The court observed inordinate delays in infrastructure development by the Cuttack Development Authority. Directing that the condition of house construction should not be insisted upon for this sector, the court allowed the petition and ordered the authority to supply the form and process
What did the court decide?
Directed the respondent to supply the transfer application form and process the 3rd party transfer within three weeks without insisting on the condition of house construction.