The petitioner claiming to have been engaged as a D.L.R. employee under the Ex
ecutive Engineer, Bhadrak (R&B) Division had earlier approached the Odisha Administrative Trib
unal in O.A. No. 1577 of 1999 praying for regularization of his service as a work charged empl
oyee. The Tribunal vide order dated 01.11.2010 directed the respondents to consider his claim
for absorption in the work charged establishment in accordance with the Government instruction
filed on 04.01.2010. The said claim of the petitioner was rejected by the Engineer-in-Chief (
Civil) Orissa vide order dated 10.10.2010 on the ground that the petitioner was not engaged as
DLR (Clerk) before 12.04.1993, which was the cut off date fixed by the Government. Challengin
g such rejection order, the petitioner preferred O.A. No. 1579 of 2011 on the ground that he w
as engaged as DLR employee under Bhadrak Division on 27.11.1991 and such fact has not been tak
en into consideration by the authority while passing the order dated 04.01.2010.