Mr. Shashikant Vitthal Kamble v. Ministry of Environment and Forest and Climate Change (Moef & Cc) New Delhi.
Case brief
What is this about?
The National Green Tribunal allowed an interim application to accept an RTI report as a Certified Compliance Report due to its non-availability on record. The main appeal was adjourned to February 2026 pending replies from respondents regarding pre-construction activities.
What did the court decide?
Interim application allowed to take RTI report on record; main appeal adjourned to 02.02.2026.