Sumit Knit Fab through Its Proprietor Rishi Jethi v. Punjab Pollution Control Board
Case brief
What is this about?
The Appellant challenged an order imposing Rs. 6.42 crore in environmental compensation by the respondent Board. The Tribunal held the order unsustainable for violating the principle of natural justice as the Board failed to disclose the methodology, quantum, or adverse inspection reports before passing the order.
What did the court decide?
The impugned order dated 24.07.2024 imposing environmental compensation is set aside, and pending IAs are disposed of.