Om Pal and Ors. vs
Case brief
What is this about?
The National Green Tribunal addressed grievances concerning illegal sand mining in the Yamuna riverbed by a project proponent who operated beyond the validity of its environmental clearance and without initial Consent to Operate. The Tribunal held that mining leases and CTOs extending beyond the environmental clearance period are invalid. The State authorities were found derelict in their duty to monitor compliance. Consequently, the Tribunal imposed exemplary costs on the proponent, directed the State to pay environmental compensation for its negligence, mandated the framing of guidelines on machinery usage, and ordered the recovery of compensation as land revenue, with the State bearing the restoration cost if recovery fails.
What did the court decide?
Respondent no. 5 to deposit Rs. 2 Lakhs as costs; Director of Mining and Geology, UPSEIAA, and UPPCB to pay Rs. 1 Lakh each as environmental compensation; MoEF&CC to issue machinery guidelines within three months; District Magistrate to determine landowner compensation; Chief Secretary to direct recovery of compensation as land revenue, with State bearing restoration cost if failure occurs due to