Dharmendra Kumar Singh v. Ministry of Environment Forest and Climate Change
Case brief
What is this about?
The National Green Tribunal disposed of an application concerning brick kilns operating in violation of environmental norms. Directions were issued for the closure of one kiln that agreed to shut down. For others, a fresh inspection was ordered to verify compliance and assess past violations, with the UPPCB mandated to submit a compliance report within three months.
What did the court decide?
Respondent No. 8 discharged from OA; fresh inspection ordered for Respondents No. 9 and 10; UPPCB directed to verify compliance, assess past violations, and submit a report within three months.