Karuppasamy v. The Commissioner
Case brief
What is this about?
Petitioner sought a mandamus for a new municipal water connection, his 2015 application having been stalled for want of distribution mains. The respondent stated distribution had now begun and connection would be given on paying Rs.7,000/- balance. The court directed the respondent to effect the connection within four weeks on payment and disposed of the petition without costs.
What did the court decide?
Direction to respondent to effect water service connection within four weeks on payment of balance Rs.7,000/-; no costs.