B.Kamroon v. The District Collector/ Sole Arbitrator
Case brief
What is this about?
Article 226 mandamus; Section 3G(5) National Highways Act 1956 compensation enhancement arbitration; extension of arbitrator mandate; Arbitration and Conciliation Act 1996 timelines (12 months award, 6 months pleadings); Section 29A extension application; District Collector Sole Arbitrator Dharmapuri; Competent Authority Special District Revenue Officer Land Acquisition NH 844 Hosur-Royakottai-Dharmapuri; award dated 05.06.2020; claim dated 20.05.2022; six-month extension; disposed of without costs; Virupatchipuram Village Dharmapuri.
What did the court decide?
Mandate of the Arbitrator extended by a further period of six months from receipt of a copy of the order; first respondent directed to conclude arbitral proceedings and pronounce the award within that period; writ petition disposed of without any order as to costs and connected miscellaneous petition closed.