B.Kamroon v. The District Collector/ Sole Arbitrator
Case brief
What is this about?
Section 3G(5) National Highways Act, 1956 enhancement claim; land acquisition compensation; Arbitration and Conciliation Act, 1996 timelines (12-month award, 6-month pleadings); Section 29A extension; extension of arbitrator's mandate under Article 226; writ of mandamus to District Collector/Sole Arbitrator Dharmapuri; National Highways 844 Hosur-Royakottai-Dharmapuri Section; award dated 02.06.2020; claim dated 13.02.2023; six-month time-bound direction to pronounce award; Madras High Court; writ petition disposed without costs; connected WMP.No.5668 of 2026 closed.
What did the court decide?
Writ petition disposed of on the above terms without any order as to costs: mandate of the Arbitral Tribunal extended by six months and the first respondent directed to conclude arbitral proceedings and pronounce the award under Section 3G(5) of the National Highways Act within six months from receipt of a copy of the order; connected miscellaneous petition (WMP.No.5668 of 2026) closed.