Sakthi Auto Component Ltd., v. Tamil Nadu Power Distribution Corporation Ltd. (Tnpdcl)
Case brief
What is this about?
Utility change / migration of wind electric generator WEG No.079204740101; conversion (not fresh execution) of Energy Purchase Agreement (EPA dated 01.10.2017) into Energy Wheeling Agreement (EWA) under own captive scheme; quashing of TNPDCL Board Proceedings No. 44 dated 01.08.2023 as repeatedly reissued orders; payment of outstanding wind energy dues along with interest within eight weeks; repeated issuance of similar board orders disapproved via followed precedent W.P.No.13729 of 2025 (order dated 22.04.2025); background chain of order dated 30.08.2019 (W.P.No.5196 of 2019 etc.), W.A.No.4189 of 2019 (18.2.2020), S.L.P.Nos.8513~8518 of 2020 (24.9.2020) and Division Bench order dated 03.01.2023 on Electricity (Late Payment Surcharge and Related Matters) Rules, 2022; Article 226 Certiorarified Mandamus; High Court of Judicature at Madras; Mohammed Shaffiq, J.; decided 20-07-2026.