B.Saraswathi v. the Union of India
Land Acquisition (National Highways) – Compensation – Interest for delay
Case brief
What is this about?
Madras High Court common order dated 25-03-2026 in WP Nos. 1814 & 1818 of 2024 (B. Saraswathi v. Union of India and others) by Krishnan Ramasamy J. Key terms: interest on land acquisition compensation; delayed deposit of compensation; National Highways land acquisition, Thiruvallur; NHAI Project Director; Nallur Village, Ponneri Taluk, Survey No. 13/1C1A; 1450 sq.mts. acquired versus 1265 sq.mts. compensated; balance 185 sq.mts.; representation dated 21.12.2023; fresh representation; disposal within 12 weeks; Article 226 writ of mandamus; Rs. 4,62,19,606/-; 9% per annum; no costs.
What did the court decide?
No substantive relief on merits; writ petitions disposed of with a direction to the petitioner to file a fresh representation claiming interest on the compensation for the period between acquisition and deposit, and a direction to the respondents to consider and dispose of it on merits and in accordance with law within 12 weeks; no costs.