M.Mayilsamy v. the Executive Engineer
Case brief
What is this about?
Madras High Court, 19.01.2026, W.P.No.17377 of 2025 (M.Mayilsamy v. Executive Engineer/Assistant Engineers, Parambikulam – Aliyar Project Scheme, Pollachi/Tiruppur/Coimbatore): natural justice — final order under Rule 6(1), Tamil Nadu Protection of Tanks and Eviction of Encroachment Act, 2007, passed the same day as the notice without opportunity to explain; Form-III notice dated 27.03.2025; impugned Assistant Engineer's order set aside; 10 days to file explanation; final orders within 4 weeks; encroachment removal/enforcement within 12 weeks of identification; Article 226 certiorari; petition allowed in part; no costs; connected W.M.P. closed; follows earlier direction in W.P.No.1935 of 2025 (23.01.2025) on disposal of encroachment complaint.
What did the court decide?
Impugned letter/order dated 27.03.2025 of the Assistant Engineer (3rd respondent) set aside; petitioner permitted to submit explanation with documents within ten (10) days of receipt of a copy of the order; respondents to consider the explanation and pass final orders within four (4) weeks thereafter; identified encroachments in the water body to be removed without further delay and enforcement actions to be completed within twelve (12) weeks of identification. No costs; connected miscellaneous petition (W.M.P.No.19699 of 2025) closed.