M/S.Jv Engineering Associate v. General Manager
Arbitration and Conciliation Act, 1996 – Section 34(2)(b)(ii)
Case brief
What is this about?
Madras High Court, OP No. 449 of 2019, decided 09.04.2026 by Senthilkumar Ramamoorthy J. - Section 34(2)(b)(ii) A&C Act petition against award dated 07.11.2018 (Sole Arbitrator V.K. Manoharan) dismissed; railway electrification contract (control rooms for TSS at Kannur South, Elattur and Tirur, Palakkad Division, Southern Railway); rider agreements for third and fourth extensions of time without price variation held binding; PVC claim under Clause 17A(ii) GCC rejected; price variation in an unconnected contract held irrelevant; mental agony and idling claims rejected for want of evidence; inadequate-reasoning ground (Dyna Technologies (2019) 20 SCC 1, cited by petitioner) not accepted; prior round involved disqualification challenge, waiver/consent under Section 12(5), O.S.A.No.119 of 2021 dated 11.08.2021, rejected SLP and remand for merits; total claims Rs. 25,71,679/- all rejected.