M/S.Jv Engineering Associate v. General Manager
Case brief
What is this about?
Keywords: Section 34 Arbitration and Conciliation Act 1996 challenge; price variation clause (PVC) refusal; rider agreements dated 15.07.2014 and 16.02.2015; Clause 17-A(ii) GCC extensions of time to 31.08.2014 and 31.12.2014; waiver letter dated 25.08.2014 disclaiming positive PVC; rider agreements void or voidable - no pleading or evidence; mental agony compensation claim in commercial contract; inadequate or improper reasoning / Section 31(3); Dyna Technologies vs Crompton Greaves (2019) 20 SCC 1; second round after O.S.A.No.119 of 2021 and Section 12(5) waiver/consent; SLP rejected, remanded on merits; Southern Railway staff quarters Tirunelveli junction Madurai Division; CORE Allahabad / Railway Electrification Chennai Egmore; JV Engineering contractors Erode; award upheld, original petition dismissed without costs.
What did the court decide?
None; the original petition was dismissed without any order as to costs and the arbitral award dated 07.11.2018 stands.