M/S.Jv Engineering Associate v. General Manager
Case brief
What is this about?
Section 34 challenge to arbitral award dismissed — price variation/PVC claim fails because rider agreement for fourth extension was executed without PVC (first three extensions carried PVC); GCC Clause 17-A(ii); rider agreement neither void nor voidable absent pleading/evidence; waiver/consent under Section 12(5) A & C Act upheld in prior O.S.A.No.119 of 2021; inadequate reasoning ground raised via Dyna Technologies Private Limited vs. Crompton Greaves Limited [(2019) 20 SCC 1] (referred); mental agony claim unsustainable in commercial contract; claims of Rs. 3,26,470/-, Rs. 1,00,000/-, Rs. 5,00,000/-, Rs. 19,588/- (total Rs. 9,46,058/-) all rejected; M/s. JV Engineering Associat Civil Engineering Contractors v. General Manager, CORE, Allahabad (Southern Railway, Palakkad Division); Madras High Court, Justice Senthilkumar Ramamoorthy, OP No. 446 of 2019, decided 09.04.2026.