Temojy v. Gnanambal
Case brief
What is this about?
Expedition of trial; Article 227 Constitution of India; Civil Revision Petition CRP No. 4262 of 2026; O.S. No. 165 of 2024; III Additional District Court Puducherry; partition and separate possession suit; senior citizens parties; written statement delay by defendants 5 and 6; eight-month disposal timeline; notice to respondents dispensed with; Madras High Court; Justice Abdul Quddhose; CMP No. 18660 of 2026 closed; no costs; order dated 27-07-2026.
What did the court decide?
Direction to the III Additional District Court, Puducherry to dispose of O.S. No. 165 of 2024, after directing defendants 5 and 6 to file their written statement within a time frame fixed by the trial Court and after framing issues and conducting trial, within eight months from the date of receipt of a copy of the order; connected miscellaneous petition (CMP No. 18660 of 2026) closed; no costs.