Suresh Kumar v. Divya
Case brief
What is this about?
CRP No. 2437 of 2025 AND CMP NO. 13988 OF 2025; High Court of Judicature at Madras; Abdul Quddhose J.; 02-07-2026; interim maintenance Rs.8,000/- per month upheld as reasonable; dismissal of revision petition against order dated 28.11.2024 of II Additional Sub Court, Coimbatore in I.A. No.1 of 2023 in H.M.O.P. No.306 of 2022; arrears payable within four weeks; main matrimonial proceeding to be disposed within six months; husband-petitioner versus wife-respondent.
What did the court decide?
Civil Revision Petition dismissed; petitioner directed to pay arrears of interim maintenance as fixed by the Court below within four weeks; Court below directed to dispose of H.M.O.P. No.306 of 2022 within six months; no costs; connected miscellaneous petition (CMP No. 13988 of 2025) closed. ¶25