The Dgm (T) And Project Director v. The District Collector and Sole Arbitrator(La)
Case brief
What is this about?
Short administrative/procedural order of the Madras High Court condoning a 480-day delay in payment of deficit court fee of Rs.14,559/- in connection with Arb.Appeal Sr.No.1120 of 2026 (CMP No.4721 of 2026). Bench: C.V.Karthikeyan, J. and K.Kumaresh Babu, J.; order authored by C.V.Karthikeyan, J.; decided 24.02.2026. Useful search terms: condonation of delay, deficit court fee, court fee condonation, arbitration appeal, miscellaneous petition, affidavit of reasons. No statutes cited, no precedents engaged, no quantum beyond the court fee figure.
What did the court decide?
Condonation of the delay of 480 days in paying the deficit court fee of Rs.14,559/-; the condonation petition was ordered. ¶8