The Superintending Engineer v. S. Arumairaj
Case brief
What is this about?
Extension of time; deposit of arbitral award amount; Section 148 CPC; C.M.P.No.4316 of 2026; Arb Appeal No. 53 of 2025; O.P.No.747 of 2016; order dated 15.10.2025; order dated 06.01.2026; automatic vacation of interim stay; inordinate delay in compliance; Finance Department approval pending; government department default; bank guarantees; 18% interest; Madras High Court Division Bench.
What did the court decide?
The Court declined to grant the further time sought, taking into account the inordinate delay in complying with its directions; the only reason offered was that proposals for allotment of funds remained pending approval with the Finance Department. ¶51