M/s. Sashwath Construction Private Limited, v. The Director / Distribution
Case brief
What is this about?
Unauthorized use of electricity; penal assessment under Section 126(5)(6), Electricity Act, 2003; penalty under section 135; review under Section 127(1) Electricity Act, 2003; Consumer Grievance Redressal Forum as competent forum; Regulation 18, Tamil Nadu Electricity Supply Code; alternative remedy/forum; writ of certiorarified mandamus; Tamil Nadu Power Distribution Corporation Limited; disposal by consent at admission stage; three-month limitation to approach CGRF; no costs.
What did the court decide?
Writ petition disposed of with directions to the petitioner to approach the concerned Consumer Grievance Redressal Forum within three months from the date of receipt of a copy of the order to raise all objections on the grounds raised in the writ petition; no costs; connected miscellaneous petitions closed. ¶38