S.K. Manikandan v. Suolifico Linea Italia (India) Pvt. Ltd.
Case brief
What is this about?
Interim Section 17-B payment direction; Suolifico Linea Italia (India) Pvt. Ltd.; S.K. Manikandan; Labour Court Puducherry; last drawn wages 20.08.2011 to May 2013; back wages; reinstatement award dated 13.08.2012; W.A. Nos. 6, 7, 8, 9 and 11 of 2024; Madras High Court; petitions partly allowed; deposit of arrears within four weeks.
What did the court decide?
Direction to the Management to deposit the arrears of the last drawn wages from 20.08.2011 to May 2013, within a period of four (4) weeks. ¶23