URC Constructions Private Limited v Chennai Metro Rail Limited; Madras High Court; Arb.O.P. (Com.Div.) No.364 of 2025; decided 14.07.2025 by Abdul Quddhose J.; substitution of Arbitrator after the Arbitrator appointed on 07.07.2025 recused for conflict of interest; appointment of Hon'ble Mr.Justice K.Govindarajan, former Judge of the Madras High Court, as Presiding Arbitrator pursuant to joint memo dated 14.07.2025/joint endorsement; dispute under contract dated 28.10.2016; balance of operative order dated 07.07.2025 unaltered; no statutory or precedent citations in the order.
What did the court decide?
Appointment of Mr.Justice K.Govindarajan, Former Judge of this Court, as Presiding Arbitrator to adjudicate the dispute between the parties (operative order cites the contract as dated 28.10.2026), with the remaining operative portion of the order dated 07.07.2025 left unaltered.