M/S.Koya &Company Construction v. the Chief Engineer
Case brief
What is this about?
Writ petition challenging recovery of extra cost incurred after contract termination for a water supply scheme. The court recalculated the recoverable amount after deducting one year's price escalation caused by the respondents' own delay in re-awarding the tender, reducing the demand to Rs.2,22,69,322/- and partly allowing the petition.
What did the court decide?
Recovery demand of Rs.16,56,58,286/- set aside; petitioner ordered to pay reduced balance of Rs.2,22,69,322/- within eight weeks; no costs; connected MP closed.