S.Kannan v. The Additional Chief Forest Conservator
Case brief
What is this about?
Petitioner, a lowest tenderer who completed construction of Forest Range Quarters, sought writ for payment of contract balance. Court directed respondents to pay within three months, imposing 6% annual interest for delays.
What did the court decide?
Direct to pay balance contract value within three months; 6% p.a. interest for delay.