agriculturists at permissible rate / concessional rate. On 16.03.2016, an inspection was conducted by the Superintendent at Mayiladuthurai Agriculture Extension Centre where they found that there was shortage of materials to the tune of Rs.4,39,248/-. Subsequently, a memo was issued to the petitioner on 03.05.2016 stating that on inspection, they found shortage of materials to the tune of Rs.4,39,248/- and held that, the petitioner as Manager is responsible for the shortage of materials and directed to remit the same to the Government Account failing which, it will be recovered from the salary of the petitioner. Thereafter, the Joint Director of Agriculture passed an order dated 20.09.2016 to recover the amount of Rs.4,39,248/- from the salary of the petitioner and the same was recovered. Aggrieved by the order of recovery dated 20.09.2016, the petitioner has preferred this present writ petition.