The Project Director v. Chan Basha
Case brief
What is this about?
The High Court directed the appellant to deposit 50% of the enhanced compensation awarded to the original petitioner pending the challenge to the arbitral award. The court modified the Single Judge's order to allow the original petitioner to apply for withdrawal of the deposited amount based on pending arbitration claims.
What did the court decide?
Deposit of 50% of enhanced compensation amount with the concerned Court within ten weeks; liberty to apply for withdrawal upon merits.