K.Ganesan v. The Commissioner
Case brief
What is this about?
The High Court of Madras disposed of a writ petition seeking demolition of unauthorized construction. The Court noted that a three-month appeal period under the Tamil Nadu Town and Country Planning Act had expired and directed the respondent Corporation to initiate further enforcement action within eight weeks. The petition was dismissed.
What did the court decide?
The respondents are directed to initiate further enforcement action as against the 5th and 6th respondents and complete the same within eight weeks.