S.Suresh v. The Secretary to Government
Case brief
What is this about?
The High Court directed the District Collector and Block Development Officer to consider the petitioner's representation for payment of Rs. 7,27,000 for a completed MGNREGA water structure. If due, payment must be made within six weeks with 7.5% interest on delay. The petition is disposed of with this direction.
What did the court decide?
Direction to respondents 3 and 5 to consider representation and decide on payment of Rs. 7,27,000 within six weeks; 7.5% interest on delay.