K. Thillaikarasi v. TamilNadu Small Industries Development
Case brief
What is this about?
The Court allowed a writ petition for the refund of Rs.6,00,000/- paid as illegal additional cost for a plot allotment. Relying on earlier orders quashing such charges, the Court directed the respondent corporation to refund the amount with interest within eight weeks.
What did the court decide?
Direction to the first respondent to refund Rs.6,00,000/- plus interest to the petitioner within eight weeks from the date of receipt of the order.