The High Court dismissed the petition to condone a delay of 944 days in preferring a first appeal. The Court held that the delay was exorbitant and unexplained, finding the claims regarding counsel's death and covid-19 insufficient. Consequently, the appeal suit was rejected at the liaison stage without costs.
What did the court decide?
The miscellaneous petition to condone delay is dismissed, and the appeal suit is rejected at the lien stage.