M/S. Immanuvel Socks - v. the Superintending Engineer
Case brief
What is this about?
Writ petition challenging a provisional assessment order for electricity theft. Court held that while the Assistant Executive Engineer was authorized to inspect, the penalty calculation was erroneous. It should have been based on 14 hours of supply for a rural feeder, not 22 hours, as per the Electricity Supply Code. Petition allowed and order set aside.
What did the court decide?
Impugned provisional assessment order dated 25.05.2010 set aside. Respondent Board directed to issue a fresh assessment order calculating penalty for 14 hours of supply as per Regulation 23(AA)7 of th