C.L.Spl.110, Veppery Primary v. The Executive Engineer,(O & M)
Case brief
What is this about?
The Court allowed a writ petition filed by a cooperative society seeking removal of electrical poles installed on its land. The Court directed the electricity corporation and panchayat respondents to shift the poles if the petitioner agrees to bear the shifting costs.
What did the court decide?
Petitioner shall pay the shifting charges; upon payment, respondents are directed to remove the electrical posts from the petitioner's land.