Malco Energy Limited, v. Tamil Nadu Electricity
Case brief
What is this about?
The High Court held that writ petitions challenging demand notices for excess power supply were not maintainable. Under the governing contract, such disputes overbilling and technical aspects are to be adjudicated by the Tamil Nadu Electricity Regulatory Commission. The Court directed the petitioners to approach the Commission, excluding limitation periods due to the regulatory body's initial non-
What did the court decide?
Writ petitions dismissed; petitioners directed to raise dispute before Tamil Nadu Electricity Regulatory Commission within one month.