Subaya Constructions Company Ltd. v. Tamilnadu Water Supply and Drainage Board
Case brief
What is this about?
The Court allowed a writ petition seeking reworking of contract terms due to the GST regime change. Relying on G.O.Ms.No.296 and a prior precedent, the Court directed the Water Board to calculate the original tax component and revise the agreement under Paragraph 10(a) within eight weeks.
What did the court decide?
Directed the Respondent Board to calculate the tax component and rework the contract price under Paragraph 10(a) of G.O.Ms.No.296 dated 09.10.2017 and enter into a revised agreement within eight weeks