K.Gopu v. The Superintending Engineer
Case brief
What is this about?
The Madras High Court allowed a writ petition challenging a refusal to correct survey numbers on electricity service connections. The Court held that failure to verify correct numbers renders the department liable and directed it to correct records upon production of land documents. No laws were cited as the Court ruled based on general administrative duty.
What did the court decide?
Respondents directed to correct survey numbers in records within four weeks upon submission of patta by petitioner.