Sree Selvavinayagar Trust, v. The Chairman
Case brief
What is this about?
The High Court quashed a demand notice for electricity arrears issued by the TNUSRB to the petitioner, holding it barred by limitation under Section 56(2) of the Electricity Act, 2003. The Court directed the adjustment of the interim stay deposit against future charges.
What did the court decide?
Impugned communication dated 28.11.2016 quashed; Petitioner's deposited sum of Rs.1,00,000- to be adjusted against future electricity charges.