M/s.Avexa Corporation Pvt. Ltd, Formerly known as M/s.Sivaswathi Constructions Pvt. Ltd. v. The Superintending Engineer, PWD Wro
Case brief
What is this about?
The applicant sought an extension of nine months to conclude arbitral proceedings citing complexity and voluminous documentation. The court, noting the respondent's lack of objection and the asserted complexity, granted the extension from the date of the order.
What did the court decide?
The time for concluding arbitration proceedings by pronouncing an award was extended by nine months from the date of receipt of the order.