payment against the final contract value, payment of withheld amount of compensation, extra work, expenses incurred in a court case under the Essential Commodities Act, transportation cost of ball-mill shells, non payment of overrun charges and loss of profits and overheads due to under utilization of mobilized men and material, extended stay and reduction in scope of work. In the aggregate, the Petitioner herein claimed a sum of Rs.2,62,89,193.06 with interest thereon at 15% per annum from 01.05.2005 till the date of payment. All the claims were refuted by the first Respondent herein and, in turn, the first Respondent herein made six counter claims towards refund of extra over run charges, supply of tools and tackles, damages, use and occupation of flat by the employee of the Petitioner, payment to a sub vendor, interest on Rs.44,87,568/- and cost of the proceedings. In the aggregate, the first Respondent counter claimed a sum of Rs.99,87,568.60. Upon completion of pleadings, the Arbitral Tribunal framed eight issues at paragraph 105 of the award. Issue Nos.3 to 5 were preliminary issues as to whether the Petitioner is entitled to invoke arbitral proceedings without complying with clause 2.5.14 of the General Conditions of Contract (GCC), whether the claims are barred by limitation and whether the first Respondent can invoke the arbitration clause without issuing notice as per clause 2.14 of