R.Balasubramanian, v. the Special Tahsildar
Case brief
What is this about?
In two appeals under Section 54 of the Land Acquisition Act, the Madurai Bench of the Madras High Court modified the award by the Land Acquisition Tribunal. The court enhanced the market value to Rs.1,178 per sq. ft. after deducting development charges and increased the construction cost to Rs.450 per sq. ft. directed the respondent to deposit the enhanced compensation.
What did the court decide?
Modified the award to fix market value at Rs.1,178/sq.ft. and construction cost at Rs.450/sq.ft.; respondent directed to deposit compensation within eight weeks.