Authority, vide letter No.52/11(PGCIL) 2015-PSP & PA-II dated 24.09.2015. The said prior approval was partially modified by letter dated 18.02.2016. In the said routes, the Erode District was not included and no environmental clearance was obtained. While so, the Transmission line should not pass through Erode and Thiruppur Districts. However, the Officials of the 4th and 5th respondents have entered upon the lands for measurement, without furnishing details in respect of erection of Tower in their lands. The paper publication issued by the Power Grid Corporation of India, does not mention her village, as a proposed route for erection of Tower lines. The Act of the 4th respondent/the General Manager, Power Grid Corporation of India, is contrary to the Rules prescribed under the Indian Telegraph Act, 1885 and Tamil Nadu Electricity Act, 2003, besides it is in violation of Article 300-A of Constitution of India (Right to Property).