V.Sumathi v. Dr.T.Muthu Perumal Clinic
Case brief
What is this about?
The Court condoned a delay of 279 days in presenting a cross petition filed in CRP Sr. No. 142869 of 2018, accepting the petitioner's explanation for the default.
What did the court decide?
The delay of 279 days in representing the cross petition was condoned.
What the court decided
C.M.P.No.22391 of 2019 in C.R.P.Sr.No.142869 of 2018
R.SURESH KUMAR, J.
This is a petition to condone
the delay of 279 days in
representing the CRP.Sr.
No.142869 of 2018.
2.Heard the learned counsel
for the petitioner and having
gone through the averments
made in the affidavit filed in
support of this petition, this Court
is inclined to accept this petition
and accordingly, this petition is
ordered and the delay is
condoned.
3.The Registry is directed to
verify whether the CRP is in
order, if it is so, number the
same and post it for admission.
23.10.2019
Sgl
Issues for consideration
1 issue framed by the court
Whether the delay of 279 days in representing the cross petition should be condoned.
Parties & counsel
- petitioner
R.SURESH KUMAR
Coram
R.SURESH KUMAR
Case details
As recorded by the court registry
Similar cases
Judgements on the same questions, provisions and authorities, from every court