Mr.P.Harikrishnan v. Mr.U.Bhagaram
Case brief
What is this about?
The High Court of Madras decreed a suit for recovery of Rs. 50,25,000 along with interest. The defendant defaulted on a letter of undertaking to pay the balance amount. The court decreed the suit for the principal sum but reduced subsequent interest from 36% to 6% per annum. Detailing the construction contract facts, the holding confirms recovery of the balance amount.
What did the court decide?
Decree for Rs. 50,25,000 principal plus 6% interest on Rs. 13,00,000 from suit date; defendant to pay within three months.